Thursday, September 13, 2012

Dock Replacement — Part IV

It is starting to look like a dock!



Wednesday, September 12, 2012

Dock Replacement — Part III

Work on the new dock is moving along.




Dock Replacement — Part II

New pilings have gone in to support the new dock.



Parts of the dock and floats are at Lakeshore Construction awaiting installation.





Tuesday, September 11, 2012

Dock Replacement on Track — Part I

Remember this?


The old dock is gone and the new dock is going in.

A work crew from Shorehill helped take apart the old dock
Pete removed the floats
Tim took things apart
Going...
Going...
Going...
Gone.
Thank you, Gayle, for keeping the community informed with your great photos. More photos from the dock rebuilding project will be posted as work progresses.

You can click on each photo to enlarge it for a better view.

Monday, September 10, 2012

Hard Work, Much Success

Shorehill members and friends worked hard during the semi-annual work party on September 8 to clean up and improve many areas of the community.

Judy and Lila pulled weeds by the boat ramp.
Carl, Gayle, Brooke, and Pete strategized.
Ron, Bill, and Chris cleaned out a drain.
Ken cleared brush on Brook Drive.
Phil and Brooke also cleared brush
on Brook Drive
Rebecka cleaned the mailboxes.
Bill and Tim painted the picnic tables.
George trimmed the hedge.
And everyone enjoyed the potluck dinner.
Thanks to Gayle and other work party organizers.

Monday, August 27, 2012

New Pier and Dock Project Begins Sept 4th - Work Party & Community Meeting Sept 8th

On September 4th Lakeshore Construction will begin the demolition of our old pier and docks, immediately followed by the construction of a new pier, docks and floats. The project will take approximately two weeks. (Sept. 4th - Sept. 18th) We will be taking photos and posting them on the blog as the project progresses. During that time you will be able to use the beach; however, there will not be any boat access nor mooring available. If you do use the beach area please be sure to stay clear of the construction site both inside and outside the water.

Thanks again to everyone for your support of this project.

We will be having a work party on September 8th which will be a great time for you to plan to come help with the work party and to see the progress on the pier, docks and floats. The work party begins at 8:30 am (sign up at the beach) and will be followed by a potluck and community meeting at 4:30 pm at the beach. Hope to see a great turnout!

Thursday, August 2, 2012

MASON COUNTY GRANTS PERMIT FOR DOCK

I just received a call from Mason County that our dock permit has been approved and is ready to be picked up.   I will be picking up the permit tomorrow and will be working with Tim at Lakeshore to determine start and end dates for the project.  We will begin sometime in August and should be finished in September.  As soon as I have more specific details I will provide another posting on the blog.    Thanks to everyone for getting your assessment payments in.   It will be well worth all our hard work and investment to have a nice new dock and pier.   Just in the neck of time :)